| 标题 |
| 石武客运专线湖北段几种CFG桩钻进设备优选试验研究(38 卷) |
| 英文标题 |
| Experimental Research on the Selection of Several Drilling Equipment Used for CFG Piles in the Hubei Section of Shijiangzhuang-Wuhan Passenger-dedicated Line |
| 摘要 |
| 铁路客运专线路基工后沉降要求十分严格,对软弱地基需加固处理,采用最多的是CFG桩加固法。针对石武客运专线湖北段地质条件,围绕长螺旋钻进法、冲击成孔法、振动沉管法、锤击沉管法和旋挖钻进法等方法的特点和适用范围进行分析,并对前2种方法进行了现场试验。结果表明,该 |
| 作者 |
| 新闻作者:高军 |
| 关键字 |