| 京津城际铁路桥梁连续梁施工工期分析(555 卷) |
| 英文标题 |
| Analysis on Construction Period of Bridge Continuous Beam on Beijing-Tianjing Intercity Railway |
| 摘要 |
| 为控制京津城际铁路桥梁关键工程的工期,桥梁连续梁施工中有19处采用支架浇筑法,20处采用悬臂浇筑法。通过对连续梁作业天数的统计分析、连续梁施工与指导性施工组织计划天数的比较、悬臂浇筑法与支架浇筑法的优缺点和施工工期分析,提出在工期紧张、条件允许的工程中,连续 |